Masonry Magazine June 1969 Page. 7

Words: Thomas Joswick, A. Groh, Roger Spahr, Herb Goetsch, Don Roethig
Masonry Magazine June 1969 Page. 7

Masonry Magazine June 1969 Page. 7
Make Money Move!

Because construction is a low-profit, high-risk industry, because the contractor loses interest on retainers and surety bonds (which combined are a form of duplication), because delayed payments cost a significant portion of profits in lost interest, a new program was born in Milwaukee. It is called "Make Money Move," or the Three M program for short.

Informal talks among construction men about problems of costs and slow payment led to formation of an ad hoc committee in recent months. This was composed of representatives of the Allied Construction Employers Association Industry Advancement Program, the Associated General Contractors of Greater Milwaukee and the Associated Public Works Contractors.

Major concerns were retainers, delays in progress payments and requirements for performance bonds.

Additional problem areas studied include (1) clarification of many statutes and ordinances, (2) reduction of arbitrary and ambiguous contract language, and (3) Necessity for standardized accounting to help determine actual project costs.

It was agreed that everyone suffers when money doesn't move-engineers, contractors, tradesmen and manufacturers. The committee, working with Thomas P. Joswick, an economic consultant, conducted a study among contractors of Milwaukee and came up with several recommendations. It presented its findings and ideas in February, 1969, to a meeting of contractors, engineers and public officials.

A 20-page booklet titled "Make Money Move" has been printed by the 3-M Committee to outline the problems, review facts and present recommendations.

Chairman of the 3-M Committee is A. J. Groh, of Jos. P. Jensen Co., a member of the Milwaukee chapter of MCAA. The Mason Contractors Association of Milwaukee voted unanimously in March to support the "Make Money Move" program. Roger H. Spahr, Secretary, reports the members and board of directors feel that reforms in this area are long overdue.

Attacking the apathy that the construction industry has allowed to slow down payments for work performed, Mr. Groh recenly explained the organized movement, "almost evangelistic in spirit," to make money move.

In a speech before contractors, engineers and public officials in Milwaukee, he recalled a Dun & Bradstreet quotation that in 1966 a general contractor's average profit per dollar of sales was 1.38 cents. He noted that the 3-M Committee study determined that withheld retainers cost the contractor roughly 20% and hidden economic costs of lags in payments chewed up nearly 30% of each profit dollar-a combined drain of as much as 50% of profits.

Major causes of the regressive flow of money in Private Construction he cited include (1) breakdown or gaps in the contractor's information on the buyer's prime source of funds and/or financing; (2) contract language ambiguities leading to payment disputes; (3) poor planning on owner's part, causing wide payment gaps, especially as completion nears; (4) diversion of retainer funds to other areas, causing hardship to prime contractor and then to sub-contractor and supplier; (5) payment delays if waivers of lien are not signed; (6) failure of contractor to familiarize himself with contract language; (7) private owners waiting for a security to mature before returning retainage.

In the Public Construction sector, major causes are (1) Institutional "paperwork constipation," costing much time and money, especially with rising use of federal funds; (2) Slow payments on about 80% of all state, highway contracts, mostly during peak construction, because the resident engineer responsible for final computations, is usually immediately re-assigned; (3) state engineering bureau procedures can require nine major steps and at least as many minor steps, involving three separate governmental bodies, the 3-M study found; (4) Laws and ordinances governing payments and retained percentages vary from one public body to the next; (5) certain public bodies convene at designated times to act on progress payments, and their schedule often creates a payment lag, (6) As the study found, one public works department can have three subdivisions, each autonomous, and one required 18 separate steps before payment certification. If no barriers are raised, collection takes an average of 35 days. (7) As in Milwaukee, the city charter can give the commissioner of public works discretionary power to set payment procedures and retained percentages.

Mr. Groh paid tribute to Milwaukee's Department of Public Works "and its very fine commissioner, Herb Goetsch, and his deputy, Don Roethig, who have taken


MASONRY STRONG Podcast Episode 19 Recap: Mike & Tom Finch
April 2025

On this episode of the MASONRY STRONG Podcast, Mike and Tom Finch join the set in Indianapolis to crack jokes, talk about how they both got started in this industry, and the ways they've seen this trade advance and evolve over the years. The Roots of a F

Echelon Masonry Introduces Ashton Brick, Its Latest Line of Artisan Masonry Veneers
April 2025

Echelon Masonry, North America’s leader in architectural masonry products and materials, announces the availability of its newest product line of artisan masonry veneers, Ashton Brick, in select states. Combining a classic brick aesthetic with durable con

MCAA Showcases Innovation at North Florida Masonry Showcase
April 2025

On Friday, April 11th, we had the pleasure of representing the Mason Contractors Association of America and our Outreach and Education Division at the North Florida Masonry Showcase. This event welcomed 15 high school students who demonstrated their growi

Thank You For Bidding In The 2025 Online Auction
April 2025

The MCAA extends a huge thank you to everyone who bid in this year’s online auction. With hundreds of bids on over 150 items, this year’s auction was another huge success. We also want to thank all of our amazing donors who put items up for auction. Wit